Nov 28, 2023
Design for Salesforce Transit Center Flange Fracture Fix Coming Soon
Fracture in Salesforce Transit Center girder found on Sept. 25. IMAGE COURTESY
Fracture in Salesforce Transit Center girder found on Sept. 25.
IMAGE COURTESY OF TJPA
Fracture in Salesforce Transit Center girder found on Sept. 25.
IMAGE COURTESY OF TJPA
Twin girders span Fremont Street.
IMAGE COURTESY OF TJPA
Shoring towers are relieving loads on twin girders supporting the hub's roof and second floor.
IMAGE COURTESY OF TJPA
Investigators for San Francisco's Transbay Joint Powers Authority are searching for the cause of brittle fractures in the tapered bottom flanges of twin 80-ft-long built-up plate girders in San Francisco's Salesforce Transit Center. With shoring in place to relieve the loads on the problem girders, which span Fremont Street, shoring contractors are turning their attention to similar parallel girders that span nearby First Street, though no cracks have surfaced there.
"Because Fremont and First streets are similarly designed, to be prudent, we have decided to [shore and] reinforce First Street as a proactive measure," said Mark Zabaneh, executive director of the TJPA, in a statement released Oct. 5.
The 4.5-block-long transit hub, which TJPA opened in August and closed in late September, spans the two city streets (ENR 10/8 p. 6). TJPA said Fremont would reopen Oct. 12, after Heedy Drayage Co., Bigge Crane and Rigging Co. and Herrick Corp., which fabricated the girders, installed shoring towers from the underside of the girders’ bottom flanges down to the foundation. First Street is only closed overnight for shoring work.
TJPA has a team scrutinizing design, fabrication, materials, welds and more. Peer-reviewed repair details will be available by about Oct. 19. The hub will remain closed until the fix is complete.
Before the problems surfaced on Sept. 25, the 1.2-million-sq-ft transit center was functioning as a bus depot, with three levels above grade and a 5.4-acre rooftop park. The third-floor Fremont and First girders, which span east to west, support a rooftop park directly above and a second-floor bus deck directly below—via a hanger at the midspan.
The transit center was designed by Pelli Clarke Pelli Architects with structural engineer Thornton Tomasetti, which is involved with the investigation and the repair. The hub was built by the Webcor/Obayashi Joint Venture. Skanska USA Civil West had the $189.1-million subcontract to furnish and erect structural steel. Shop drawings were detailed by Candraft Detailing Inc., a sub of Skanska.
Bottom-flange cracks are near the 8-ft-deep midspan of each shop-welded girder. The more serious fracture is 4 in. deep and runs 2.5 ft through the entire 2.5-ft-wide flange, made of 4-in.-thick plate.
The hanger plate slots through the bottom flange with tabs welded the full depth of the girder's web. "Cracks are only in the flange and do not touch the hanger or welded tab," says Dennis Turchon, TJPA's senior construction manager.
Under the flange, the hanger stub is bolted to a wide flange vertical member, in tension. The WF hangs the second floor.
TJPA has not released any shop drawings. All others parties involved, including the peer reviewer led by Degenkolb Engineers, declined to comment.
However, TJPA is releasing an electronic repository of reviews, design reports, contracts, inspections, etc., about the project. It is available on tjpa.org.
In one posted document, Degenkolb's Loring A. Wyllie, who chaired the structural peer review panel, wrote to the city's Dept. of Building Inspection on April 15, 2014, that the committee "finds that the current drawings for the above-grade structural package are in general conformance with the San Francisco Building Code." The panel then recommended the city issue a building permit.
Nadine M. Post, ENR's editor-at-large for the design and construction of buildings, is an award-winning journalist with more than 40 years of experience covering buildings-related trends, issues, innovations and challenging projects. Post has written about many industry giants, including nine ENR Award of Excellence winners. And she has covered disasters, failures and attacks, including the 1993 bombing and the 2001 destruction of the World Trade Center. A sampling of Post's project stories includes the redevelopment of the World Trade Center; the 828-meter-tall Burj Khalifa; Los Angeles’ Disney Concert Hall; and Seattle's Experience Music Project, Central Library, Bullitt Center and Rainier Square Tower. In 1985, Post wrote McGraw-Hill's book Restoring the Statue of Liberty (1986) for the restoration's architects—Richard S. Hayden and Thierry W. Despont.